                                                     PROJECT STATUS




Brief Description of the Project ( On-going)


Construction of Ground + 3 floors residential building in Yaba area of Lagos state comprising of 18 nos  2 bedroom apartments.

Project Team
Architects:                                                     Bl Design and Services 
Structural Engineers:                                    Civilsys Structural Engineer.
Services Consultant:                                     Edge Consultants

Contractor:                                                   Blueline Urban Projects 

Status of Work   

-85% Completion achieved 






Previous Pictures (May, 2018)




                        


Sample Apartment as Completed Onsite







No comments:

Post a Comment

3032 APARTMENTS - COMPLETION UPDATE

https://bluelinurbanprojects.blogspot.com/2019/05/3032-apartments-completion-update.html  PROJECT COMPLETED  Brief ...