Monday 3 September 2018

Junior Boys' Hostel for Corona Secondary School, Agbara






Brief Description of the Project
Junior Boys' hostel for Corona Secondary school comprising of Basement level,Ground + 3 floors)  approximately 3,500 m2. 

Duration of Project: March 2016 - August 2018

Project Team

Main Contractor:                Blueline Urban Projects Ltd.
Architects:                         Studio OLA
Structural Engineers:          Sanni Ojo & Partners
Quantity Surveyor:             Sanya Sam & Associates
Services Consultant:           KOA Consultants Limited
Nominated Sub-contractors:  Kenol Nig. Ltd 
                                         Metallum Ltd. 

Status of Work


- PRACTICAL COMPLETION



Project Progress Pictures 























































                          
                                                   
                                              

No comments:

Post a Comment

3032 APARTMENTS - COMPLETION UPDATE

https://bluelinurbanprojects.blogspot.com/2019/05/3032-apartments-completion-update.html  PROJECT COMPLETED  Brief ...